A job can be done by 8 men in 12 days. How many days will it take for 4 men to complete the same job?
  1. 24 days
  2. 30 days
  3. 36 days
  4. 48 days

Questions & Step-by-Step Solutions

A job can be done by 8 men in 12 days. How many days will it take for 4 men to complete the same job?