If A can finish a work in 20 days and B can finish it in 30 days, how long will
Practice Questions
Q1
If A can finish a work in 20 days and B can finish it in 30 days, how long will they take to finish the work if A works for 10 days and then B works for 10 days?
15 days
20 days
25 days
30 days
Questions & Step-by-Step Solutions
If A can finish a work in 20 days and B can finish it in 30 days, how long will they take to finish the work if A works for 10 days and then B works for 10 days?