Q1
If A can do a work in 15 days and B can do it in 25 days, how long will it take for A and B to complete the work if A works for 5 days and then B works for 5 days?
10 days
12 days
15 days
20 days
Questions & Step-by-Step Solutions
If A can do a work in 15 days and B can do it in 25 days, how long will it take for A and B to complete the work if A works for 5 days and then B works for 5 days?